Allied

High-Speed Train Flanges Factory

High-Speed Train Flanges Factory

Project Name

High-Speed Train Flanges Factory

Owner: Engineering Institution For Civil Works ( EICW )
Consultant: Allied For Engineering And Projects

Date of implementation: 2022

Location: Helwan – Alkurimat Road, Helwan, Egypt

Project Main Component: Supply and install the following systems:

  • Electrical Works: Transformer, Generator, Panel Boards, Low Voltage Cables, Cable Trays, Lighting, Lighting Switches, Power, Sockets And Earthing.
  • Light Current Works: Fire Alarm System, IP-CCTV Network, Structured Cabling System And Fiber Network.
  • HVAC Works: Fans, Duct work, Air outlets, Volume & Fire Dampers, Cable Trays And MCC’S.
  • Fire Fighting Works: Fire Fighting Pumps, Piping System, Fire suppression System, Fire Hose Cabinets, Fire Extinguishers And Valves.
  • Additional Mechanical Works: Air Compressed Station, Filtered Water Station, Piping System, And Valves.